HIGH RISE RESIDENTIAL TOWERS

  • Multi Storeyed / HighRise Apartment first of its kind situated in heart of the city , Srinagar Colony, Hyderabad was taken up the Company.
  • Three such Towers were Constructed in the same premises.
    • High Rise structure
    • Total Area: 150,000 Sft.
  • Value: Rs. 220.00 Lakhs
  • Scheduled date of Completion: 31.03.2003
  • Actual date of Completion: 20.03.2003

RETAINING WALL

  • Construction of Retaining wall and Compound Wall, 8 Nos. Garages, 24 Nos Ministers Quarters at Road No.12, Banjara Hills, Hyderabad.
  • Specialities: Designing and Construction.
  • Value: Rs. 205.63 Lakhs
  • Scheduled date of Completion:18th July, 2003
  • Actual date of Completion: 18th July, 2003

HEALTH CARE CENTRES

  • 14 Nos Health Care Centers 50 bedded Hospitals at Davanagere, Karnataka including Internal & External Electrifications works
  • Specialities:
    • Lumpsum Tender Project
    • Hospitals located at various places, TOTAL - 70000 Sft.
  • Value : Rs. 403.98 Lakhs
  • Scheduled date of Completion: 16th Nov, 2004
  • Actual date of Completion: 16th Nov, 2004

WAR MEMORIAL

  • War Memorial Stup at Gymkhana Grounds, Secunderabad including External Fašade Lighting
  • Stup with Ashoka Chakra cladded with granite
  • Specialities: Cladding the vertical structure with granite
  • Value: Rs. 80.75 Lakhs.2003
  • Scheduled Date of Completion: May - 03
  • Actual Date of Completion: May - 03

AP SECRETARIAT BLOCK

  • Construction of 2 Nos. H-Block at Secretariat including internal & External Electrification and Air Conditioning, Hyderabad
  • Specialities: 100,000 Sft.
  • Value: Rs. 550.00 Lakhs
  • Scheduled Date of Completion: Aug - 04
  • Actual Date of Completion: Aug - 04

HOSTELS / ENGG DEPT

  • Construction New Girls Hostel, Chemical Engg. Deptt., Ist Floor of Guest House at JNTU College at Ananthapur District including Internal & External Electrification Works.
  • Specialities: 200,000 Sft.
  • Value of Works: Rs. 376.20 Lakhs
  • Scheduled Date of Completion: 07.04.2005
  • Actual Date of Completion: 07.04.2005

RESIDENTIAL FLATS

  • Construction of Residential 140 Nos. Flats for Karnataka Housing Board, at Bangalore including Internal & External Electrification Works.
  • Specialities: Area: 150,000 SFT.
  • Value of Works: Rs. 1167.00 Lakhs
  • Scheduled Date of Completion: Oct - 07
  • Actual Date of Completion: Oct - 07

EMBANKMENT WORKS

  • Construction of Embankments and GSB works, from ORAI to Bhoginepur, NHAI Project
  • Specialities: Embankment Works
  • Value of Work: Rs. 503.82.00 Lakhs
  • Date of Commencement: Nov 2007
  • Time Period for Completion: March - 08

CIVIL WORK

  • Name of the Work: Constructions of Civil Work and Hydro Mechanical Works of Sorang Hydroelectric project (2 x 50 MW=100 MW) in the state of Himachal Pradesh.
  • Specialties: Hydro Electric Power Plant Work.
  • Value of Work: Rs. 1400.00 Lakhs
  • Date of Commencement: March 2008
  • Time Period for Completion: 12 Months

IRRIGATION PROJECTS

  • Construction of Right Earth and closing Gorge Portion, Excavation of Left and Right Main Canals including construction of Right Head sluice CM & CD Works Distributory System for Gundlakamma Reservoir Project
  • Specialities: Irrigation Project on Turnkey Basis
  • Value of Work: Rs. 600.00 Lakhs
  • Date of Commencement: June 2007
  • Scheduled Date of completion: Mar - 08

POWER TRANSMISSION & DISTRIBUTION

  • Construction of 0.433/33KV Switchyards - 10 Nos and connected 33KV Lines - 200 KMS on Lattice Towers with DOG Conductor and connecting the 3MW wind Power to Grid at Tadipathri, Anathapur District
  • Main Contractor: RRV Constructions Ltd
  • Specialities: 33KV Lines - 200 KMS on Lattice Towers with DOG Conductor on Hilly Terrain
  • Value of Works: Rs. 385.00 Lakhs
  • Scheduled Date of Completion: 06.10.05
  • Actual Date of Completion: 15.09.05

ELECTRICAL DISTRIBUTION & SYSTEM IMPROVEMENT WORKS

  • System Improvement works at Latur under Goathan Feeder Separation Scheme, MSEDCL
  • Main Contractor: NCC Ltd End Client: MahaDiscom Value: Rs. 2640.00 Lakhs Scheduled Date of Completion:31st May 2008 Actual Date of Completion: 31st May 2008

ELECTRICAL TRANSMISSION & DISTRIBUTION WORKS

  • Total Erection Part on Back to Back basis and for supply of selected materials of infra plan phase-1 in Osmanabad & Latur Circles Under Infra Phase I, MSEDCL
  • Main Contractor: NCC Ltd
  • End Client: MahaDiscom
  • Value: Rs. 7837.12 Lakhs
  • Scheduled Date of Completion:29 Sep 2011
  • Actual Date of Completion: 29 Sep 2011

MEP WORKS

  • Internal / External Electrification Works including providing Air-Conditioning for 1500 beded Hospital at Srikakulam
  • Main Contractor: Lanco Ltd
  • End Client: APHMHIDC
  • Value: Rs. 500.00 Lakhs
  • Scheduled Date of Completion: 31.03.2009

IT PARKS

  • Maan Sarovar Properties Development (P) Ltd, Chennai
  • Specialities: IT Park
  • Area: 4,00,000 Sft.
  • Value of Work: Rs. 1800.00 Lakhs
  • Date of Commencement: March 2008
  • Time Period for Completion: 12 Months

BRIDGES & FLYOVERS

  • Construction of ROB - 4 Nos, Southern Railway, Chennai
  • Specialities: Bridges under Railways
  • Value of Work: Rs. 1890.00 Lakhs
  • Date of Commencement: Nov 2007
  • Time Period for Completion: 13 Months

CULTURAL COMPLEX

  • Multipurpose Cultural Complex at KavuriHills, Hyderabad including Internal & External Electrification Works
  • Auditorium with 500 persons seating capability
  • Specialities: Special Structure on Rock
  • Area: 100,000 sft. Area
  • Value: Rs. 438.55 Lakhs
  • Scheduled Date of Completion: 20th Feb 2006.